Vineyards at Marsh Creek Amphitheater

General Information

Project Description:

The Vineyards at Marsh Creek Amphitheater is comprised of a 750-1000 seat amphitheater along with amenities that may include a wedding venue, sculpture garden, promenade and a future community arts/events center.  The project is located on a 31-acre site, west of Vineyards Parkway between Reserve Place and Miwok Avenue.  The current budget for the project is $8.1M.

The first Public Workshop will be held virtually on Thursday, October 21, 2021 at 6:00pm

Topic: Vineyards at Marsh Creek Amphitheater Public Meeting
New Date: Thursday, October 21, 2001
New Time: 6:00 p.m.
Location: (Virtual) Zoom Link - https://brentwoodca-gov.zoom.us/j/75487006220

 

 

Schedule Overview:

Project Initiation (March 2021) Program Development: (April through July 2021) – CURRENT PHASE
Comprised of 2 stakeholder workshops and 1 public workshop.

Conceptual / Schematic Design (Summer Thru Fall 2021)
Comprised of Drawings drafted and presented at 2 stakeholder workshops and 1 public workshop.

Bridging Documents & 30% Design (Winter 2021)
Design-Build Team Selection (Spring 2022)

Begin Construction (Summer 2022)
Construction Completion (Summer/Fall 2023)